Landslide Repair in Pademangan Accelerated

Jakarta Water Resouces Dept. continues to speed up work on landslide repairs in Ciliwung River, RT 01/RW 08, Ancol Urban Village, Pademangan, North Jakarta.

Every day we're deploying 40 officers. It's targeted to be completed by the end of December

Until now, part of which is fixed up to 77 meters, or about 60.6 percent of the total length of 127 meters that were damaged.

Governor Monitors Landslide Location in Kalisari

Jakarta Water Resources Dept.'s River and Coast Flow Systems Section, Robert Rajagukguk stated that his side divided the work into two segments. The first stage of the construction up to 77 meter long is now completed already.

"Currently the second phase of the repair is up to 50 meters length," he expressed, Wednesday (11/28).

He added that the Ciliwung River has five meters height. The work itself has been ongoing since October 21, 2018.

"Every day we're deploying 40 officers. It's targeted to be completed by the end of December," he stated.

Linked News
Popular News indeks
  1. Rano: CIEIE 2026 to Catapult Jakarta’s MSMEs onto the International Stage

    access_time25-08-2026 remove_red_eye754 personBudhi Firmansyah Surapati
  2. Jakarta Deploys 120 Personnel to Counteract Traffic Disruption for Today’s Protests

    access_time27-08-2026 remove_red_eye736 personAldi Geri Lumban Tobing
  3. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye666 personDessy Suciati
  4. Transjakarta Commits to Transport Equality Across the Seribu Islands

    access_time24-08-2026 remove_red_eye562 personAldi Geri Lumban Tobing
  5. Transjakarta Resumes Operations with Strategic Service Adjustments

    access_time28-08-2026 remove_red_eye540 personAldi Geri Lumban Tobing