 Proses Perbaikan Turap Ambrol di Ancol Capai 60 Persen

Landslide Repair in Pademangan Accelerated

Jakarta Water Resouces Dept. continues to speed up work on landslide repairs in Ciliwung River, RT 01/RW 08, Ancol Urban Village, Pademangan, North Jakarta.

Every day we're deploying 40 officers. It's targeted to be completed by the end of December

Until now, part of which is fixed up to 77 meters, or about 60.6 percent of the total length of 127 meters that were damaged.

Governor Monitors Landslide Location in Kalisari

Jakarta Water Resources Dept.'s River and Coast Flow Systems Section, Robert Rajagukguk stated that his side divided the work into two segments. The first stage of the construction up to 77 meter long is now completed already.

"Currently the second phase of the repair is up to 50 meters length," he expressed, Wednesday (11/28).

He added that the Ciliwung River has five meters height. The work itself has been ongoing since October 21, 2018.

"Every day we're deploying 40 officers. It's targeted to be completed by the end of December," he stated.

Linked News
Popular News indeks
  1. Jakarta Administration Steps Up Proactive Fire Prevention Efforts

    access_time09-10-2026 remove_red_eye396 personDessy Suciati
  2. 10,000 Participants Join People's Sports Festival at Velodrome

    access_time04-10-2026 remove_red_eye359 personNurito
  3. Public Health Alert, Jakarta Urged to Anticipate Influenza A Surge

    access_time07-10-2026 remove_red_eye330 personFakhrizal Fakhri
  4. Kelapa Gading-Pulogadung Link Road Targeted for Completion in 2027

    access_time09-10-2026 remove_red_eye314 personDessy Suciati
  5. Moving Day, Apuran River Locals Clear Out for New Flood Pump

    access_time09-10-2026 remove_red_eye312 personBudhi Firmansyah Surapati