You don't have javascript enabled. Good luck with that.
Pencarian
 Proses Perbaikan Turap Ambrol di Ancol Capai 60 Persen

Landslide Repair in Pademangan Accelerated

Jakarta Water Resouces Dept. continues to speed up work on landslide repairs in Ciliwung River, RT 01/RW 08, Ancol Urban Village, Pademangan, North Jakarta.

Every day we're deploying 40 officers. It's targeted to be completed by the end of December

Until now, part of which is fixed up to 77 meters, or about 60.6 percent of the total length of 127 meters that were damaged.

Governor Monitors Landslide Location in Kalisari

Jakarta Water Resources Dept.'s River and Coast Flow Systems Section, Robert Rajagukguk stated that his side divided the work into two segments. The first stage of the construction up to 77 meter long is now completed already.

"Currently the second phase of the repair is up to 50 meters length," he expressed, Wednesday (11/28).

He added that the Ciliwung River has five meters height. The work itself has been ongoing since October 21, 2018.

"Every day we're deploying 40 officers. It's targeted to be completed by the end of December," he stated.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye870 personTiyo Surya Sakti
  2. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye655 personTiyo Surya Sakti
  3. Several Microtrans Routes Diverted

    access_time31-01-2026 remove_red_eye369 personAldi Geri Lumban Tobing
  4. Pramono: Jakarta Government Acts Swiftly to Tackle Flooding

    access_time30-01-2026 remove_red_eye369 personDessy Suciati
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye362 personDessy Suciati
close